N2 - This paper proposes an optimization approach to plan the maintenance personnel and spare parts in a multiple echelon stocking system. In this system, for each failure requested by group p\in P-{j}, if the jth local warehouse has available inventory, maintenance personnel with a spare part will be supplied by it, otherwise, the resources request will be routed to other warehouses. The optimal stock policy (\underline{S}) which can minimal total cost is the optimized target, including holding cost, ordering cost, maintenance cost and transshipment cost. A heuristic approach is used to obtain \underline{S}. Using the heuristic methods, a complex system consisted of one plant, two central warehouses and three local warehouses is considered, the system served for three groups with two machines, and five modules is consisted in each equipment. The simulation results show the model's effectiveness.
AB - This paper proposes an optimization approach to plan the maintenance personnel and spare parts in a multiple echelon stocking system. In this system, for each failure requested by group p\in P-{j}, if the jth local warehouse has available inventory, maintenance personnel with a spare part will be supplied by it, otherwise, the resources request will be routed to other warehouses. The optimal stock policy (\underline{S}) which can minimal total cost is the optimized target, including holding cost, ordering cost, maintenance cost and transshipment cost. A heuristic approach is used to obtain \underline{S}. Using the heuristic methods, a complex system consisted of one plant, two central warehouses and three local warehouses is considered, the system served for three groups with two machines, and five modules is consisted in each equipment. The simulation results show the model's effectiveness.
KW - Joint optimization
KW - greedy heuristic
KW - maintenance personnel
KW - spare parts
UR - https://www.scopus.com/pages/publications/85079616523
U2 - 10.1109/IEEM44572.2019.8978686
DO - 10.1109/IEEM44572.2019.8978686
M3 - 会议稿件
AN - SCOPUS:85079616523
T3 - IEEE International Conference on Industrial Engineering and Engineering Management
SP - 965
EP - 967
BT - 2019 IEEE International Conference on Industrial Engineering and Engineering Management, IEEM 2019
PB - IEEE Computer Society
T2 - 2019 IEEE International Conference on Industrial Engineering and Engineering Management, IEEM 2019
Y2 - 15 December 2019 through 18 December 2019
ER -