Through two methods of numerical simulation and similar simulation, the failure problems of the open-pit slope under the condition of combining open-pit mining with underground mining were analyzed and discussed. The results show that the failure of the open-pit slope is a gradual process, in order to guarantee the normal open-pit mine production works well, the explored boundary must be controlled well by the vertical stature of safe mining. By the analysis of the similar simulation, the mining order is optimized.
| 源语言 | 英语 |
|---|---|
| 页(从-至) | 1346-1350 |
| 页数 | 5 |
| 期刊 | Meitan Xuebao/Journal of the China Coal Society |
| 卷 | 33 |
| 期 | 12 |
| 出版状态 | 已出版 - 12月 2008 |
指纹
探究 'Mechanism of the slope failure of horizontal thick coal seam under the condition of combined mining' 的科研主题。它们共同构成独一无二的指纹。引用此