Distributed resource constrained multi-project scheduling problem with cooperative-game based negotiation mechanism

  • Dongning Liu
  • , Zhe Xu*
  • , Feifei Li
  • *此作品的通讯作者
  • Beihang University

科研成果: 期刊稿件文章同行评审

摘要

The distributed resource constrained multi-project scheduling problem (DRCMPSP) involves the individual scheduling of multiple projects and the coordination of shared resources among the projects. It is the crux of solving the DRCMPSP that designing an effective mechanism to obtain the necessary projects' information in order to coordinate the global resources. We constructed the hierarchical model with the global objective of optimizing the total delay cost of the multi-projects under the consideration of different unit project. And we designed a cooperative-game based negotiation mechanism to allocate the global resources and the hierarchical model was solved by the proposed phased evolution algorithm under the account of the information asymmetry in DRCMPSP and the self-interested project decision makers. According to the computational results of instances in MPSPLIB, it is effectively to decrease the total delay cost of the multi-projects that using the cooperative-game based negotiation mechanism and the approach is available to various problems with different sizes and utilization factors. In addition, in order to get low delay cost the autonomous agents should participate in the cooperative game and behave honestly and meanwhile a high-quality solution will be obtained.

源语言英语
页(从-至)1507-1516
页数10
期刊Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice
39
6
DOI
出版状态已出版 - 1 6月 2019

学术指纹

探究 'Distributed resource constrained multi-project scheduling problem with cooperative-game based negotiation mechanism' 的科研主题。它们共同构成独一无二的学术指纹。

引用此